UNIK Construction Engineering Lesotho (PTY) LTD

  • Digging of trenches and laying of cable
  • Installation of poles and lights
  • Installation of kiosks
  • Termination of electrical circuits on main kiosk
  • Earthing and bonding of the poles and kiosk
  • Testing and commissioning of electrical installations

Lesotho National Development Corporation (LNDC)

  • Procurement and management
  • Removal of old high bay lights and lighting circuit wiring
  • Wiring of factory lighting circuit
  • Installation of LED high bay lights and fluorescent fittings
  • Rewiring of factory distribution box and replacement of  circuit breakers
  • Installation of transformer surge arrestors
  • Testing and commissioning

Lesotho Electricity Company (LEC)

  • Excavation of cable trench and site backfill
  • 240mmX4c cable laying
  • Termination of cable in both ends
  • Generator bus – bar section to incoming section of the LV panel
  • Testing and commissioning

Lesotho National Development Corporation (LNDC)

  • Procurement and management
  • Removal of old high bay lights and lighting circuit wiring
  • Wiring of factory lighting circuit
  • Installation of LED high bay lights and fluorescent fittings
  • Rewiring of factory distribution box and replacement of  circuit breakers
  • Installation of transformer surge arrestors
  • Testing and commissioning

Revenue Services Lesotho (RSL)

General maintenance to Maseru bridge, Oblate offices, Training centre offices, Government offices, Railway offices, Warehouse, Hoohlo stores, Airport

  • Electrical maintenance
  • Plumbing maintenance
  • Installation of drywall and aluminium partition
  • Paving works
  • Installation of ceiling

Letshego Financial Services

Engaged as electrical sub contractor

  • Installation of kiosk
  • Installation of LV cables to designated distribution boxes
  • Installation of cable ladder, trunking, cable trays, and cables baskets
  • Cutting and chasing of walls for power and lighting circuits
  • Wiring and installation of lighting and power points
  • Installation of plugs, lights and switches
  • Installation of distribution boxes and termination of electrical circtuits
  • Earthing and bonding of building structure
  • Testing and commissioning

Ministry of Public Works and Transport

Engaged as sub contractor

  • Installation of kiosk
  • Installation of LV cables to designated distribution boxes
  • Installation of cable ladder, trunking, cable trays, and cables baskets
  • Cutting and chasing of walls for power and lighting circuits
  • Wiring and installation of lighting and power points
  • Installation of plugs, lights and switches
  • Installation of distribution boxes and termination of electrical circtuits
  • Earthing and bonding of building structure
  • Testing and commissioning

Roads Directorate

  • Digging of trenches and laying of cable
  • Installation of poles and lights
  • Installation of kiosks
  • Termination of electrical circuits on main liosk
  • Earthing and bonding of poles and kiosk
  • Testing and commissioning

Lesotho Electricity Company (LEC)

  • Pegging and setting out of Medium Voltage (MV) line route
  • Excavation and planting of MV pole structures
  • Stringing and tensioning of Fox conductor
  • Full installation of MV transformer structure, including  100KVA pole mounted transformer and crowfoot earthing system on both MV and LV sides
  • Installation of LV distribution, kiosks, stays, struts and all associated line hardware
  • Commissioning and safety testing conducted under strict supervision of LEC